Features:

Very small footprint water treatment plant. Using its own water source as a substitute to other expensive raw  water source.

Completion Date: January 2002

Contract Value: 12,000,000 MB

The Client had awarded the contract to Aquathai based upon the innovative approach and fast track project delivery. The turnkey construction include the new water treatment plant at the existing pond receiving water from the nearby stream. The scope of work include:

  • 200 m3/h water treatment plant
  • Raw water pumping intake and station
  • Clarifier
  • Filter
  • Softener
  • GAC Filters
  • Chemical system
  • Brine Regeneration
  • Electrical control cabinet and instrumentation
  • including pH controller
  • Rehabilitation of treated water tank