Upgrading and Improvement of Water treatment plant at Suranaree University

Upgrading and Improvement of Water treatment plant at Suranaree University

Suranaree

Client: University of Technology of Suranaree

Location: Nakorn Ratchasima

Features:Upgrading and improvement work with a new advance water treatment plant

Completion Date: November 1998

Contract Value: 49,600,000 MB

The construction of new water treatment plant and related works to improve the old water treatment plant of the University. The design and construction services include:

  • Supply and installation of a new 200 m3/h WTP
  • Raw water Pumping Station
  • Upgrade the existing plant to the automatic system
  • Raw water reservoir of 50,000 m3
  • Raw water transmission and distribution water pipe